Opinions of the environmental protection acceptance expert group on the completion of the renovation and expansion project of the production line with an annual output of 30,000 tons of high-voltage insulators, 400,000 composite insulators and 300 tons of

Time: 2019-12-21 11:41:00 Views:

 Jiangxi GaoQiang Ceramic Insulator Group Co.,Ltd hosted the "Jiangxi GaoQiang Ceramic Insulator Group Co.,Ltd with an annual output of 30,000 tons of high-voltage insulators and 400,000 Reconstruction and expansion project of composite insulators and 300 tons of supporting plastic material production line "Completed Environmental Protection Acceptance Technical Review Meeting. There were 7 representatives and experts (list of experts attached) from Jiangxi GaoQiang Ceramic Insulator Group Co., Ltd (construction unit and acceptance report preparation unit). The participating experts and representatives surveyed the project site, listened to the construction unit's report on the project's environmental protection performance and acceptance monitoring report preparation unit on the project's completed environmental protection acceptance monitoring report, and reviewed relevant materials. According to the requirements of "Regulations on Environmental Protection Management of Construction Projects" (Order No. 682 of the State Council) and "Interim Measures for Environmental Protection Acceptance of Construction Projects" (Guohuangui Environmental Assessment [2017] No. 4), after careful discussion, the following acceptance opinions were formed.
 1. Project overview
 This project is a reconstruction and expansion project. Jiangxi GaoQiang Ceramic Insulator Group Co.,Ltd invests 108 million yuan in Xintian Village, Luxi Town, Luxi County to build an annual output of 30,000 tons of high-voltage insulators, 400,000 composite insulators and 300 tons of supporting glue assembly. Raw material project, the project area is 17402m'. The project has a quota of 350 people, with an annual production time of 300 days and 8 hours of production. The environmental protection investment of the project is 810,000 yuan, accounting for 0.75% of the total investment of the project. This acceptance only checks the contents of Jiangxi GaoQiang Ceramic Insulator Group Co., Ltd's reconstruction and expansion project and its supporting facilities.
 2. Environmental protection implementation
 1. "Three Simultaneous" situation
 Jiangsu Lvyuan Engineering Design and Research Co., Ltd. compiled the "Jiangxi GaoQiang Ceramic Insulator Group Co., Ltd. Annual Production of 30,000 tons of high-voltage insulators, 400,000 composite insulators and 300 tons of supporting plastic assembly raw material production line renovation and expansion project" in April 2019, and On June 25, 2019, it obtained the environmental assessment approval from the Luxi County Environmental Protection Bureau (Lu Environmental Assessment [2019] No. 29).
 The environmental protection facilities of this project have been completed. The environmental protection facilities have been designed, constructed and put into operation at the same time as the main project, and have the conditions for the completion and acceptance of environmental protection.
 2. Environmental management and environmental protection system
 Jiangxi GaoQiang Ceramic Insulator Group Co., Ltd attaches great importance to the establishment and management of environmental protection files, and has formulated complete environmental management rules and regulations, covering various contents such as the management of governance facilities.
 3. Environmental protection facilities construction situation
 After on-site inspection, the environmental protection facilities of this project are operating normally.
 (1) Waste gas treatment
 Project waste gas mainly includes furnace flue gas, injection molding waste gas, and self-made glaze dust. Furnace flue gas is discharged through 15m high exhaust gas, injection molding waste gas is collected by pipes and then discharged through UV photolysis device + activated carbon adsorption + 15m high exhaust gas, self-made glaze dust is discharged unorganized, no canteen is built inside the factory, each The waste gas pollutants are discharged after being properly treated.
 (2) Wastewater treatment
 The wastewater generated during the operation period of the project is mainly domestic wastewater and production wastewater. The domestic sewage is reused for plant greening after the integrated sewage treatment equipment, the squeezed mud wastewater enters the sedimentation tank and is recycled for use, and the cooling water is recycled for use.
 (3) Noise control
 The main noise sources during the operation period of the project are the noise generated by the operation of mechanical equipment such as ball mills, mud mills, vibrating screens and compacting machines. During the design and equipment ordering of the project, noise control requirements have been put forward to the manufacturer, and measures have been taken for noise insulation and noise reduction for high-noise equipment, and vehicles are managed, and whistling is prohibited.
 (4) Solid waste
 The solid waste of the project is the domestic waste of employees and the unqualified products of the inspection process, sedimentation tank slag, trimming process leftovers, dust ash, waste activated carbon and UV photolysis waste lamp tubes. After collection, the domestic waste is entrusted to the environmental sanitation department to clear and transport, and the unqualified products are sold and comprehensively utilized. The sedimentation tank is directly reused for production. There is no sediment from the domestic sewage. The trimming process scraps are broken and used as the raw material for plastic packaging. The dust and slag are reused in the glaze making process, and the waste activated carbon and waste UV photolysis lamps are handed over to a qualified unit for processing. The hazardous waste of the project before being processed is temporarily stored in the hazardous waste temporary storage room.
 3. Acceptance investigation and monitoring results
 From November 24th to 25th, 2019, Jiangxi Tianke Testing Technology Co., Ltd. conducted an acceptance survey and monitoring of the completion of the project, during which the environmental protection facilities were operating normally. The following results are derived from the "Completed Environmental Protection Acceptance Monitoring Report" (TK1911013) provided by Jiangxi Tianke Testing Technology Co., Ltd.
 1. Wastewater monitoring conclusion
 The wastewater from the enterprise is not discharged, so the production wastewater is not monitored. The on-site acceptance investigation found that the domestic sewage of the enterprise was reused for plant greening after being integrated into the sewage treatment equipment. The squeezed mud wastewater enters the sedimentation tank and is recycled for use after precipitation, and is not discharged outside. The cooling water is recycled and not drained.
 2. Exhaust gas monitoring conclusion
 During the acceptance monitoring period, the emission concentrations of organized particulate matter, sulfur dioxide, nitrogen oxides, and fluoride all meet the requirements of the “Pollutant Emission Standard for the Ceramic Industry” (GB25464-2010) and amendments to the furnace firing flue gas. Hydrocarbon meets the "Synthetic Resin Industry Pollutant Emission Standard" (GB31572-2015). Unorganized non-methane total hydrocarbons meet the "Synthetic Resin Industry Pollutant Emission Standard" (GB31572- -2015), and the fugitive dust emission meets the "Comprehensive Emission Standard of Air Pollutants" (GB16297-1996) Table 2 of the fugitive emission concentration limit value.
 3. Noise monitoring conclusion
 During the acceptance and monitoring period, the noise at the boundary of the plant complies with the standard limit of category 2 in the "Environmental Noise Emission Standard at the Boundary of Industrial Enterprises" (GB12348- -2008).
 4. Solid waste conclusion
 The solid waste of the project is the domestic waste of employees and the unqualified products of the inspection process, sedimentation tank slag, trimming process leftovers, dust ash, waste activated carbon and UV photolysis waste lamp tubes. After collection, the domestic garbage is entrusted to the environmental sanitation department for unified-cleaning, transportation and disposal. "Unqualified products are sold and comprehensively utilized. The sedimentation tank sediment waste is directly reused in production. No sediment is generated in the domestic sewage. The trimming process scraps are broken and used as plastic packaging materials. The dust and slag are reused in the glaze making process, and the waste activated carbon and waste UV photolysis lamps are handed over to a qualified unit for processing. The hazardous waste of the project before being processed is temporarily stored in the hazardous waste temporary storage room.
 Four, acceptance conclusion
 After on-site inspections, the acceptance team carefully reviewed relevant materials, and after full discussion, it is believed that the project has basically implemented the environmental assessment requirements and various environmental protection measures in the approved documents. On the premise of completing the rectification opinions put forward by the acceptance team, the project conforms to the completion environment Protect the acceptance conditions.
 5. Suggestions and requirements
 1. According to the requirements of "Interim Measures for Environmental Protection Acceptance Acceptance of Construction Projects" and "Technical Guidelines for Environmental Protection Acceptance of Construction Projects for Pollution Impact", according to the actual situation of the enterprise, improve the relevant content in the acceptance monitoring report and verify the actual construction of the project Is it consistent with the EIA and approval?
 2. Enterprises should set up temporary storage rooms for hazardous wastes in accordance with the relevant requirements of the "Hazardous Waste Storage Pollution Control Standards" (GB18597-2001) and its 2013 standard amendments, and establish hazardous waste accounts; enterprises should follow the "General Industrial Solid Waste Storage , Pollution Control Standards for Disposal Sites (GB18599-2001) and its 2013 revision list and environmental impact assessment documents require the establishment of a general industrial solid waste temporary storage room, and the waste ceramics stacked in the open air are stored in the general industrial solid waste temporary storage room , And establish-general industrial solid waste ledger.
 3. Enterprise glaze workshops should be equipped with diversion ditch and collection tank. If a leakage accident occurs, the overflow glaze can be temporarily stored in the collection tank.
 4. Supplement the pollution-free complaint and dispute certificate, the floor plan of the plant area, mark the location of the environmental protection facilities of the project in the floor plan, standardize the drawings and attachments, and strengthen the text verification.
 5. In accordance with environmental management requirements, strengthen the standardized construction of sewage outlets and set up exhaust gas signs.
 6. ​​Other opinions of experts and participants.
 Expert Group:

December 21, 2019